#1 |
|
Project involved changing out on the run (8) 8.0" Cooling Condenser Riser pipes while the Worldwide Boeing Computer System remained on line. |
|
|
|
|
|
|
|
|
|
|
#2 |
|
This image highlights just how severe the corrosion had become on the Condenser Riser Pipes. |
|
|
|
|
|
|
|
|
|
|
#3 |
|
CRYOSTOP International Pipe Freeze Technician preps the first 8.0" vertical riser which is fed from a 20.0" header just below the surface. |
|
|
|
|
|
|
|
|
|
|
#4 |
|
The SC-800 CRYO-LATOR Chamber develops a dependable and workable freeze plug in approximately 1 hour / 30 minutes. |
|
|
|
|
|
|
|
|
|
|
#5 |
|
Maintenace staff remove the last of the defective condenser risers and old block valves. |
|
|
|
|
|
|
|
|
|
|
#6 |
|
Old block valve and spool piece are lifted out. |
|
|
|
|
|
|
|
|
|
|
#7 |
|
Pipe Flange is preped for new block valve. |
|
|
|
|
|
|
|
|
|
|
#8 |
|
New block valve is lifted into place. Note the exposed freeze plug. |
|
|
|
|
|
|
|
|
|
|
#9 |
|
New block valve is bolted into place. |
|
|
|
|
|
|
|
|
|
|
#10 |
|
First block valve is preped to except the new spool piece and second block valve. |
|
|
|
|
|
|
|
|
|
|
#11 |
|
Welders had to fabricate each new riser. |
|
|
|
|
|
|
|
|
|
|
#12 |
|
Image shows the freeze plug through the newly installed block valve. |
|
|
|
|
|
|
|
|
|
|
#13 |
|
New block valve in place. |
|
|
|
|
|
|
|
|
|
|
#14 |
|
Shows the first completed riser with both new block valves. |
|
|
|
|
|
|
|
|
|
|
#15 |
|
Maintenance staff works to install new block valve. |
|
|
|
|
|
|
|
|
|
|
#16 |
|
Project Completed. Image shows all (8) of the Condenser Risers completed with each riser having 2 new block valves. |
|
|
|
|
|
|
|