#1 |
|
The (2) Old Block Valves To Be Changed Out Are Just Inside The Basement Wall. |
|
|
|
|
|
|
|
|
|
|
#2 |
|
Experienced On-Site CRYOSTOP™ Freeze Techs Setup The First CRYO-LATOR® Freeze Seal Chamber. |
|
|
|
|
|
|
|
|
|
|
#3 |
|
Project Setup Is Almost Complete. |
|
|
|
|
|
|
|
|
|
|
#4 |
|
Dual CRYO-LATOR Chambers are ready. Note the vent extensions for safe removal of LN2 vapors. |
|
|
|
|
|
|
|
|
|
|
#5 |
|
CRYOSTOP tech records LN2 consumption. |
|
|
|
|
|
|
|
|
|
|
#6 |
|
Both simultanous plugs are complete and set. |
|
|
|
|
|
|
|
|
|
|
#7 |
|
One of the old block valves is changed out. |
|
|
|
|
|
|
|
|
|
|
#8 |
|
Open flanges are prepared and ready to except new valve. |
|
|
|
|
|
|
|
|
|
|
#9 |
|
View of the 24" freeze plug as seen through the open flanges. |
|
|
|
|
|
|
|
|
|
|
#10 |
|
New block valve is being installed. |
|
|
|
|
|
|
|
|
|
|
#11 |
|
Overhead view of freeze chambers. |
|
|
|
|
|
|
|
|
|
|
#12 |
|
Overhead view of complete work area. |
|
|
|
|
|
|
|
|
|
|
#13 |
|
New valves are installed and CRYO-LATOR freeze plugs are complete. |
|
|
|
|
|
|
|
|
|
|
#14 |
|
Experienced Techs Removing The Chambers |
|
|
|
|
|
|
|
|
|
|
#15 |
|
Chambers have been removed. |
|
|
|
|
|
|
|
|
|
|
#16 |
|
Both new block valves are secured in place. |
|
|
|
|
|
|